Scenario: Tanja wants to organise a Park(ing) Day outside her school — she will block off a parking space for a day and host a furniture-building workshop with her classmates. She has already found a carpenter friend to lead the workshop. Help sort the remaining tasks into the right Kanban columns, then reveal her board to compare.
0/6 correct. Drag the tasks into the Kanban columns, then click Reveal to check your answer.

Tasks to Sort

Contact municipality for parking permission
Organise snacks and drinks
Check permission for music / speakers
Making posters
Writing the Instagram post
Found a carpenter to lead the workshop
Backlog
Not started yet
Priority
Needs to happen soon
In Progress
Currently being done
Done
Completed
🎉 Excellent! You sorted all 6 tasks correctly!
Tanja's Recommended Board & Reasoning

Contact municipality for parking permission

→ Priority

Getting legal permission to block a parking space is the most critical step — without it, the entire event cannot happen. This must be tackled first.

Organise snacks and drinks

→ Backlog

Important for the atmosphere, but not time-sensitive yet. It can be planned once the event date and space are confirmed.

Check permission for music / speakers

→ Priority

Another permission that needs to be resolved early so the programme can be planned around whatever is allowed.

Making posters

→ In Progress

Promotional materials need to go up well before the event. Tanja has already started this to build buzz and spread the word around school.

Writing the Instagram post

→ Backlog

Social media content can be drafted once the key details — date, location and programme — are confirmed. There is no need to rush this before permissions are secured.

Found a carpenter to lead the workshop

→ Done

Already completed — the scenario tells us Tanja has already found a carpenter friend. This can be considered finished.